Critical path and baseline: reading a construction schedule that slips
The critical path is the longest chain of linked activities from start to finish: any day lost on it moves the completion date. The baseline is the approved schedule frozen at the start, so you can measure every slip against it. Together they tell you not only that the job is late, but which activity is driving it and how much margin the others still have.
- Topic
- Schedule management, critical path method
- Reading time
- 5 min
- Updated
- October 6, 2026
- Also in
- Français
What the critical path method actually computes
The critical path method (CPM) takes the activities, their durations in working days and their logical links, and runs two passes. The forward pass gives each activity its earliest start and earliest finish. The backward pass, starting from the project finish, gives its latest start and latest finish. The difference is the total float: how many days the activity can slip without moving the project finish. Activities with zero float form the critical path.
Free float is the other number worth knowing: how many days an activity can slip without delaying the next activity. On a job site, free float tells the superintendent how much room a trade has before it gets in the next trade's way.
A small example
| Activity | Duration | Predecessors | Early dates | Total float |
|---|---|---|---|---|
| A. Excavation | 5 | None | Days 1–5 | 0 |
| B. Footings and foundation walls | 8 | A | Days 6–13 | 0 |
| C. Underground plumbing | 4 | A | Days 6–9 | 4 |
| D. Slab on grade | 3 | B, C | Days 14–16 | 0 |
| E. Structural steel | 10 | D | Days 17–26 | 0 |
| F. Site services | 6 | A | Days 6–11 | 15 |
| G. Roofing | 7 | E, F | Days 27–33 | 0 |
The critical path is A, B, D, E, G: 33 working days. Underground plumbing can slip four days before it delays the slab; site services have fifteen days of float. If the steel fabricator announces a five-day delay, the roof finishes five days late. If the plumber is three days late, nothing moves, but the plumbing has only one day of float left and deserves attention.
Getting the logic right
- Link every activity to at least one predecessor and one successor. An activity hanging loose has meaningless float, and the critical path stops being reliable.
- Prefer logic to imposed dates. A “start no earlier than” constraint is sometimes needed (a permit, a delivery), but a schedule full of fixed dates no longer computes anything.
- Use finish-to-start by default, start-to-start with a lag for overlapping trades (drywall can start two days after framing starts on a floor), and keep the reason for each lag.
- Schedule on a working calendar with the real holidays, construction holidays and weather assumptions of the region, or every duration is wrong by the same few percent.
- Keep activities short enough to be measured: as a rule of thumb, no longer than two reporting periods.
Baseline versus current schedule
The baseline is a frozen copy of the approved schedule: dates, durations and, for cost control, the budget spread over time. The current schedule keeps moving as the job progresses. Without a baseline, you only know where the job is going; with it, you know how far it has drifted and since when. It is also the reference for earned value: planned value is read from the baseline, not from the current schedule.
Many project managers keep two baselines: the initial one, never touched, for the record and for claims, and a current one, reset only after an approved change that changes the scope or the contract dates. Resetting the baseline just because the job is late hides the problem; resetting it after an approved extension is correct.
| Milestone | Baseline | Current | Variance |
|---|---|---|---|
| Structure complete | March 13 | March 20 | +5 working days |
| Building enclosed | May 8 | May 22 | +10 working days |
| Substantial completion | September 25 | October 9 | +10 working days |
Reading a slipping finish
When the projected finish moves, ask three questions in order.
- Which activity is driving it? Follow the critical path back from the finish until you find the activity whose dates moved. That is where the delay comes from, not necessarily where it shows up.
- Is the critical path the same as last month? A new critical path means an activity that had float has used it up. It often points to a procurement problem (late shop drawings, long-lead equipment) rather than to the work on site.
- Is the delay excusable? An owner's change, a late answer to an RFI or a differing site condition may justify a time extension; your own crew's productivity does not. Document it while the facts are fresh.
Then decide how to recover: resequence (work two floors in parallel), add a crew on the critical activity only, overlap with a start-to-start link, or accept the delay and notify. Crashing a non-critical activity costs money and gains nothing.
Schedule variance in days, not only in dollars
Earned value expresses schedule variance in dollars (SV = EV − PV). Site teams think in days. Report both: the finish variance in working days against the baseline, and SPI for the trend. Near the end of the job, trust the days: SPI drifts back to 1.00 even on a late project. For the weeks ahead, translate the critical path into a three-week look-ahead the foremen can act on.
Applying it in Teyvor
Teyvor's schedule computes the critical path on your working calendar as you link tasks in the Gantt chart, shows each task's float, and keeps two baselines, the initial one and the current one. The overview compares the projected finish with the contract finish and the baseline; when an approved change carries a schedule impact, it is applied only after you confirm it, so the baseline stays a deliberate decision.
Key takeaways
- The critical path is the chain of activities with zero total float: a day lost there is a day lost at the finish.
- Float is a shared margin; watch activities whose float is shrinking.
- Freeze a baseline before measuring; reset it only after an approved scope or time change.
- When the finish slips, trace the critical path back to the activity that moved.
- Report schedule variance in working days, with SPI as a trend.
Questions and answers
Can a project have more than one critical path?
Yes. Two chains can have the same zero float, which makes the schedule more fragile: a delay on either one moves the finish.
Who owns the float?
It depends on the contract. Many contracts say float belongs to the project, available to whichever party needs it first; others are silent, which leads to disputes. Read the scheduling clauses before the first claim.
Is CPM part of the PMP exam?
Yes. The critical path method, forward and backward passes, float and schedule compression are part of the schedule management content covered by the PMP exam.
How often should a construction schedule be updated?
At least monthly with the progress report, and weekly for the look-ahead. Record actual start and finish dates, remaining durations and percent complete, then let the logic recompute the dates.
Apply these methods on your next project: schedule, budget, changes and billing in one place. No credit card.
Try Teyvor free for 30 daysRelated guides
All guides- The three-week look-ahead: running the next 15 working days of a job siteSchedule management, short-interval planning
- Earned value management in construction: a project manager's guideCost management, earned value
- Change order management: integrated change control on a construction projectIntegrated change control, change orders
PMP and PMBOK are registered marks of the Project Management Institute, Inc. Teyvor is not affiliated with or endorsed by PMI.